Accomplishments


During Phase 1 of the project, Phycal completed preliminary site engineering activities and developed a preliminary site design. Currently, Phycal is finalizing NEPA, federal, state and local permitting and detailing site designs prior to authorization of site engineering and construction of the facility. Throughout the project, Phycal will also be conducting research and development activities at a subpilot-scale facility in Highland Heights, OH. Phycal’s partners are also expanding cutting edge unit processes in this field. The Phycal team is composed of scientists, engineers, and management; all of whom have extensive experience in their respective fields.


Project Details