CCS and Power Systems

Advanced Energy Systems - Gasification Systems


A Technology To Mitigate Syngas Cooler Fouling - Phase II


Performer: Reaction Engineering International

Project No: SC0004499


Contacts, Duration, and, Cost

Contacts

Jenny Tennant
Gasification Systems Technology Manager 
National Energy Technology Laboratory 
3610 Collins Ferry Road 
P.O. Box 880 
Morgantown, WV 26507-0880 
304-285-4830 
jenny.tennant@netl.doe.gov

Robert Romanosky 
Crosscutting Research Technology Manager 
National Energy Technology Laboratory 
3610 Collins Ferry Road 
P.O. Box 880 
Morgantown, WV 26507-0880 
304-285-4721 
robert.romanosky@netl.doe.gov

Steven Seachman 
Project Manager 
National Energy Technology Laboratory 
3610 Collins Ferry Road 
P.O. Box 880 PO3B 
Morgantown, WV 26507-0880 
304-285-5255 
steven.seachman@netl.doe.gov

Mike Bockelie 
Principal Investigator 
Reaction Engineering International 
77 West 200 South 
Salt Lake City, Utah 84101 
801-364-6925  
bockelie@reaction-eng.com


Duration
Award Date: 08/04/2010
Project Date: 05/14/2014


Cost
DOE Share: $1,098,895.00
Performer Share: $0.00
Total Award Value: $1,098,895.00


Project Details