CCS Demonstrations

Clean Coal Power Initiative (CCPI) -


Recovery Act: W.A. Parish Post-Combustion CO2 Capture and Sequestration Project


Performer: Petra Nova Parish Holdings LLC

Project No: FE0003311


Contacts, Duration, and Cost

Contacts

Michael Knaggs
Director
Office of Major Demonstrations
National Energy Technology Laboratory
3610 Collins Ferry Road
P.O. Box 880
Morgantown, WV 26507-0880
304-285-4926
michael.knaggs@netl.doe.gov

Ted McMahon
Project Manager
National Energy Technology Laboratory
3610 Collins Ferry Road
P.O. Box 880
Morgantown, WV 26507-0880
304-285-4865
ted.mcmahon@netl.doe.gov

David Greeson
Participant Project Manager
Vice President, Commercial
Petra Nova LLC, an NRG Company
1000 North Post Road, Suite 240
Houston, TX 77055
281-407-1253
David.Greeson@nrgenergy.com

DOE financial assistance awards reference a Total Project Cost that may differ from the total project cost figures published by recipients.  In this case, the DOE Total Project Cost does not include the cost associated with the combustion turbine, pipeline, or oil field development and operation, among other miscellaneous costs.   DOE funds are focused on the design and construction of the carbon dioxide capture system and monitoring, verification, and accounting activities that are performed to ensure that the carbon dioxide is permanently sequestered. 


Duration
Award Date: 06/01/2010
Project Date: 12/31/2019


Cost
DOE Share: $166,804,425.00
Performer Share: $302,376,195.00
Total Award Value: $469,180,620.00


Project Details